PURE SODA ASH PROJECT, AT MAGADI SODA
This project was completed on time and included rock excavation of 7000 CM and
basement of 2700 SM for machine foundations, such as pre-heater towers, cooling
rooms, and clinics. (The major materials were supplied by the Lead Consultants).
This Project consisting of:
Completion of machine foundation, etc., including external and civil works.
Basically, it was an industrial project.
Testimonial from the client.
William John
Chairman & Chief Executive
Key Points From The Project
Write short details here.Â
Project images
Project Information
Client Name:
Magadi Soda
Category:
Start Time:
05-04-2005
End Time:
04-04-2006
Budget:
Ksh 242,767,500.00