VIHIGA DIST. HOSPITAL, AT MBALE TOWN
This is the first stalled project of M.O.P.W. which was completed on time apart
from 7 weeks delay due to weather conditions.
This Project consisting of:
Completion of 200 bed multistorey Hospital Facilities, Mortuary Block, 40 Nos. Staff Housing of 6,240 SM Area and External and Civil Works.
Testimonial from the client.
William John
Chairman & Chief Executive
Key Points From The Project
Write short details here.Â
Project images
Project Information
Client Name:
Ministry of Public Works
Category:
Start Time:
10-08-2005
End Time:
10-03-2006
Budget:
Ksh 98,925,590.00